ADOT making progress on Interstate 10 construction project in Tucson

TUCSON, Ariz. (13 News) – The Arizona Department of Transportation discussed the progress on a major construction project along Interstate 10.

Read more Firefighters fully contain Hazen Fire near Buckeye

Drivers will begin driving on a newly constructed section of Interstate 10 this weekend.

Traffic will be shifted onto more than a mile of new concrete pavement from Park Avenue to Country Club Road.

This marks a major milestone in a $600 million project to reconstruct and widen I-10 from Kino Parkway to Alvernon Way.

ADOT says the project is now 40% complete.

Along with the traffic shift, ADOT wants drivers to be aware of other changes in the work zone.

  • The westbound I-10 off-ramp to Park Avenue will close for up to 90 days.
  • The eastbound I-10 on-ramp at Park Avenue will close for up to 90 days.
  • The westbound I-10 on-ramp at Palo Verde Road will close permanently.

Work began in June 2025 with the goals of reducing delays and enhancing safety. Major project features include adding a third lane in each direction of I-10 and building two interchanges.

Read more Chance the Rapper bringing ‘Coloring Book’ anniversary tour to Phoenix

Considered the largest highway construction project in southern Arizona history, this improvement will:

  • Widen I-10 to three lanes in each direction between Kino Parkway and Alvernon Way with auxiliary lanes
  • Reconstruct the interchange at Kino Parkway
  • Construct a new interchange Country Club Road that will provide access for traffic that currently uses the interchange at Palo Verde Road to allow for safer traffic movements to and from I-10
  • Remove the existing interchange Palo Verde Road
  • Construct a new westbound on-ramp at the Alvernon Way interchange
  • Construct an I-10 undercrossing to connect the North and South Kino Sports Complex

Throughout the project, ADOT says it will maintain two lanes of travel in each direction on I-10 during peak travel times while maintaining access to businesses.

Construction is expected to continue through 2028.

Are you streaming 13 News?

Watch a free live stream of Tucson Now and 13 News at TucsonNow.Live.

Be sure to download the free Tucson Now app, which you can find on Apple and Google.

If you are using a desktop computer, you can use your mobile device to scan the QR code below.

Read more Las Vegas man faces felony charge in cat drowning case, Clark County DA says

You can submit your breaking news or weather images here.

By admin

Leave a Reply

Your email address will not be published. Required fields are marked *