WILLCOX, AZ (AZFamily) — SpaceX has promised billions in grid upgrades and no groundwater use to run its proposed Arizona data center, according to Cochise County’s board chair, but Arizona’s top prosecutor is urging the county to delay a vote on the project.
Read more Infectious disease deaths rise among Arizona children, state report finds
At full build-out, the campus would consume 6 gigawatts of power, nearly 20% of the state’s total power-generating capacity, according to Arizona Attorney General Kris Mayes. The power demand is part of the reason her office is asking for the delay.
What SpaceX has proposed
SpaceX has pledged to invest $50 billion in what it calls its Cochise Supercomputer Campus. The hyperscale data center would cover nearly 750 acres.
According to the company’s application to the county, SpaceX is proposing nine buildings, each of which would be 500,000 square feet.
Board of Supervisors chair addresses concerns
Board of Supervisors Chair Frank Antenori was asked about his reaction when he learned SpaceX was interested in Cochise County.
“I didn’t believe it,” Antenori said. “It was a big surprise. Hard to believe. And now it’s looking pretty good.”
Antenori said SpaceX has addressed several of the county’s concerns. He said the company has said it will use no groundwater to run the facility, has pledged to spend $3.6 billion to upgrade the power grid and will follow county dark-sky rules.
Jobs estimate
Antenori was asked what the project would mean for Cochise County.
“When it’s fully built out, you’re probably looking at about a thousand jobs, half of which are likely going to be jobs that folks right out of high school can obtain,” he said.
SpaceX originally put out the jobs estimate. The Brookings Institution, a nonpartisan public policy group, published a research paper on the topic. Greg Wright, a professor at the University of California, Merced, was a co-author.
“If you think about the number of jobs that are created at some of these kind of more mid-sized data centers that used to be our large data centers and you scale that up to the size that we’re thinking about here with these AI complexes, then, you know, it’s plausible, I think,” Wright said.
Antenori said the project will also create another 1,500 secondary jobs. Wright questioned that figure.
“That sounds a little high to me for a small rural community, but it could be something there,” Wright said.
Antenori and Wright both said the project could help the county’s finances.
“It will definitely benefit our schools and our hospital districts, our fire districts and whatnot in the county,” Antenori said.
Next steps
The Planning and Zoning Commission must first approve the land use. The county then must work out a development agreement, which the county says is legally binding. The developer then must get a building permit for the project.
The county estimates the process could be complete by April or May.
Mayes asked the commission to delay its land use vote, which is scheduled for about three weeks from now.
Arizona’s Family Investigates reached out to all nine members of the commission. Some had not heard of the letter or the request, but none of them said they’d immediately respond. A county public information officer said that the county has no new information to report.
See a spelling or grammatical error in our story? Please click here to report it.
Do you have a photo or video of a breaking news story? Send it to us here with a brief description.
Do you have a story you want us to investigate? Tell us about it by contacting us.
Read more Suspect facing murder charge in deadly Tucson crash